YPF Anticipates Argentina LNG Construction Start in February

The Argentina LNG project, spearheaded by YPF alongside Italian energy major Eni and XRG, the international investment arm of Abu Dhabi's state-owned ADNOC, could commence construction works next February. This was announced by Horacio Marín, president and CEO of YPF, who noted that three financial instruments remain to be finalized to complete the project's financing structure—one of the most ambitious energy infrastructure initiatives on Argentina's agenda.
According to statements from the state oil company's chief executive, the February timeline is tentative and subject to parallel progress in financial negotiations involving international banks and consortium partners. The finalization of these instruments is critical for civil works and installation to proceed on the company's projected schedule.
What is Argentina LNG and Who is Involved
Argentina LNG is a project designed to establish Argentina as an exporter of liquefied natural gas, leveraging unconventional gas resources from the Vaca Muerta formation in Neuquén province. The initiative encompasses wellhead gas production development, transportation via trunk pipelines, and construction of a liquefaction plant to supply LNG to international markets, a format that facilitates maritime transport to buyers in Europe and Asia.
The partnership structure brings together YPF as the local operator with extensive knowledge of the Neuquén basin, Eni, a leading European energy major with significant global liquefaction project experience, and XRG, the international investment vehicle of ADNOC, Abu Dhabi's state petroleum company, which in recent years has expanded its diversification strategy into gas and LNG assets outside the Middle East. This combination aims to leverage technical expertise, financial capacity, and access to target markets for a project of this scale.
Financing: The Outstanding Variable
Marín's statements underscore that despite announcing a construction start date, the project remains in a critical financial phase. The executive mentioned three outstanding instruments without publicly specifying their nature, suggesting ongoing negotiations with banking entities, multilateral credit institutions, or consortium partners were still underway at the time of his remarks.
For projects of this magnitude, financial close typically requires a combination of equity contributions from partners, long-term structured debt from international banks, and in some cases guarantees or hedges linked to final product sales contracts. The typical sequence indicates that finalizing these instruments precedes massive capital disbursements for construction, though certain preliminary works may proceed in parallel.
Horacio Marín, YPF president and CEO, indicated that Argentina LNG construction works could begin in February, though he clarified that three financial instruments must still be finalized to complete the project's financing structure.
Project Phases: From Feasibility to Construction
The announcement of a potential construction start in February marks a turning point from earlier feasibility and engineering study phases the project has undergone since conception. In the gas and LNG industry, the transition from study phases to actual construction—known as FID, or final investment decision—represents a significant milestone, as it signals formal partner commitment to disburse necessary funds and initiate civil works, equipment installation, and liquefaction and export infrastructure deployment.
It should be noted that construction commencement does not equate to LNG production startup, which will require a construction period that typically spans several years for comparable international projects. Marín's February reference specifically denotes the beginning of construction activities, not plant commissioning or export initiation.
Vaca Muerta Context and the RIGI Role
Argentina LNG fits within the broader strategy to monetize Vaca Muerta gas resources, which in recent years have shown sustained production growth driven by YPF operations and other private operators. The need for a large-scale export pathway, such as that offered by LNG, reflects constraints posed by domestic and regional markets to absorb the full volume of gas the basin could produce in coming years.
In this context, the Large Investment Incentive Regime (RIGI), enacted by the national government as part of the Bases Law, has been repeatedly identified as a key instrument to attract investments of the magnitude Argentina LNG requires, offering fiscal, exchange, and customs stability to participating projects. Available materials do not specify whether Argentina LNG has already formally adhered to the regime, so this point warrants additional confirmation from the involved companies.
Expected Impact and Next Steps
Beyond investment and employment figures that may emerge in upcoming project phases, Argentina LNG's materialization is viewed by the energy sector as a decisive step toward establishing Argentina as a net hydrocarbon exporter, in a scenario where Vaca Muerta gas competes with other global supply sources for Asian and European markets. Financial structure closure in the coming weeks will be the key metric to confirm whether Marín's February construction start date is actually realized.
YPF has not provided further details on total committed investment, projected liquefaction capacity, or the complete timeline for different project phases—aspects that are likely to be communicated in greater detail as financial negotiations progress and the construction start date approaches.